File #: R-2021-109    Version: 1 Name: Resolution by NMA Approving Assignment of Contract from Cabbiness to Garver
Type: Resolution Status: Passed
File created: 3/16/2021 In control: City Council
On agenda: 3/23/2021 Final action: 3/23/2021
Title: RESOLUTION NO. R-2021-109: A RESOLUTION OF THE TRUSTEES OF THE NORMAN MUNICIPAL AUTHORITY ASSIGNING CONTRACT K-1617-105 WITH CABBINESS ENGINEERING, L.L.C., TO GARVER, L.L.C, AND TRANSFERRING ASSIGNMENT OF ALL RIGHTS AND DUTIES AS "CONSULTANT" UNDER CONTRACT K-1617-105 TO GARVER, LLC.
Attachments: 1. City Council Staff Report, 2. Resolution R-2021-109, 3. Cabbiness Notice of Assignment - City of Norman, 4. Garver, LLC Acceptance Letter - City of Norman
Title
RESOLUTION NO. R-2021-109: A RESOLUTION OF THE TRUSTEES OF THE NORMAN MUNICIPAL AUTHORITY ASSIGNING CONTRACT K-1617-105 WITH CABBINESS ENGINEERING, L.L.C., TO GARVER, L.L.C, AND TRANSFERRING ASSIGNMENT OF ALL RIGHTS AND DUTIES AS "CONSULTANT" UNDER CONTRACT K-1617-105 TO GARVER, LLC.

Body
BACKGROUND: On March 14, 2017, the Norman City Council approved the design contract (K-1617-105) with Cabbiness Engineering, for the James Garner Avenue project from Acres Street to Flood Avenue, and Cabbiness began preliminary design for the project.

On August 27, 2019, the Norman City Council approved Contract Amendment No. One for contract K-1617-105 in the amount of $2,275 for the design of the James Garner Avenue Project from Acres Street to Flood Avenue.

DISCUSSION: Since beginning design on this project, the Norman Municipal Authority has been informed that Cabbiness Engineering has merged with Garver, LLC, and therefore that Cabbiness seeks to transfer its rights and duties under this contract as "Consultant" to Garver, LLC for completion of the project. Garver, LLC has in-house right-of-way acquisition services. By amending the design contract to include right-of-way acquisition services, the City gains the advantage of having a single contractor handling both the design and acquisition of the remaining required parcel.

By separate contract amendment, Amd. No. 2 to K-1617-105, the NMA and Garver seek to amend the scope of Contract K-1617-105, and its Amd. No. 1, to increase the contract amount to accommodate changes in scope of the engineering design from the original contract, including:

* Right of Way Acquisition Services for required parcels associated with the James Garner Phase 2 - Acres Street to Flood Avenue Project.

Garver, LLC has proposed a design fee of $5,675 (see Contract Amendment #2) to provide right-of-way acquisition services for the James Garner Extension project (NFB004). The previous contract and amendments with Cabbiness Engineering...