File #: K-1819-97 CO #1    Version: 1 Name: Change Order for 24th Ave. E, Phase 2
Type: Contract Status: Passed
File created: 1/26/2021 In control: City Council
On agenda: 2/9/2021 Final action: 2/9/2021
Title: CHANGE ORDER NO. ONE TO CONTRACT K-1819-97: BY AND BETWEEN THE CITY OF NORMAN AND H&H PLUMBING & UTILITIES, INC., INCREASING THE CONTRACT AMOUNT BY $11,259.40 FOR A REVISED CONTRACT AMOUNT OF $2,341,759.40 FOR THE 24TH AVENUE EAST WATER LINE RELOCATION PROJECT, PHASE 2, AND FINAL ACCEPTANCE OF THE PROJECT.
Attachments: 1. City Council Staff Report, 2. Change Order No. 1, 3. Location Map
Title
CHANGE ORDER NO. ONE TO CONTRACT K-1819-97: BY AND BETWEEN THE CITY OF NORMAN AND H&H PLUMBING & UTILITIES, INC., INCREASING THE CONTRACT AMOUNT BY $11,259.40 FOR A REVISED CONTRACT AMOUNT OF $2,341,759.40 FOR THE 24TH AVENUE EAST WATER LINE RELOCATION PROJECT, PHASE 2, AND FINAL ACCEPTANCE OF THE PROJECT.

Body
BACKGROUND: On November 22, 2011, the Norman City Council approved Programming Resolution R-1112-62, requesting federal funds for the 24th Avenue East Widening Project. This resolution states the City's commitment to adhere to the terms and conditions of a federally funded project including engineering design, acquisition of all necessary rights-of-way and relocation of utilities and encroachments at 100% the City's cost. In return, the Association of Central Oklahoma Governments (ACOG), through the Oklahoma Department of Transportation (ODOT), agrees to provide 80% of the construction cost, estimated at $7,831,000, and administration of the construction with the matching (20%) share from the City of Norman.

On August 28, 2012, the citizens of Norman voted in favor of a General Obligation Bond issue to finance the local share of eight transportation/stormwater improvement projects. One of the eight 2012 bond projects is the 24th Avenue East Bond Project (please see the attached location map showing the project boundaries). The total estimated project cost including design, utility relocations, right-of-way, construction and construction management is $15,388,000. The City's share is estimated to be $7,518,000.

Proposed improvements for the 24th Avenue East Widening Project include:

1. Widen two miles of roadway from two lanes to four lanes
2. New traffic signal at 24th Avenue East and Meadowood Boulevard
3. Intersection improvements at 24th Avenue East/Meadowood Boulevard and 24th Avenue East /Robinson Street.
4. Interconnect traffic signals on 24th Avenue East from Lindsey Street to Robinson Street
5. Continuous sidewalks and accessibilit...