File #: K-1920-78 CO#1    Version: 1 Name: Frank & Hughbert Drainage Improvement
Type: Contract Status: Passed
File created: 7/1/2020 In control: City Council
On agenda: 7/14/2020 Final action: 7/14/2020
Title: CHANGE ORDER NO ONE TO CONTRACT K-1920-78: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND EMC SERVICES, L.L.C., INCREASING THE CONTRACT AMOUNT BY $14,661.85 FOR A REVISED CONTRACT AMOUNT OF $93,238.85 FOR THE FRANK AND HUGHBERT STREETS DRAINAGE IMPROVEMENT PROJECT, FINAL ACCEPTANCE OF THE PROJECT, AND BUDGET TRANSFER BETWEEN PROJECT ACCOUNTS.
Attachments: 1. City Council Staff Report, 2. Change Order No 1 to K-1920-78 Frank and Hughbert Streets Drainage Project.pdf, 3. Final Pay App for K-1920-78 Frank and Hughbert Streets Drainage Project.pdf, 4. Frank and Hugbert Streets Drainage Project Location Map.pdf
Title
CHANGE ORDER NO ONE TO CONTRACT K-1920-78: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND EMC SERVICES, L.L.C., INCREASING THE CONTRACT AMOUNT BY $14,661.85 FOR A REVISED CONTRACT AMOUNT OF $93,238.85 FOR THE FRANK AND HUGHBERT STREETS DRAINAGE IMPROVEMENT PROJECT, FINAL ACCEPTANCE OF THE PROJECT, AND BUDGET TRANSFER BETWEEN PROJECT ACCOUNTS.

Body
BACKGROUND: In response to multiple citizen complaints regarding flooding on Frank Street and Hughbert Street west of Jones Avenue over several years, the City's fiscal year 2019-2020 (FYE 2020) Capital Fund budget included a project to address the problem. In 2019, the Public Works Stormwater Division began working with Cardinal Engineering to design improvements to the drainage system on both Frank and Hughbert Streets (see attached map). Cardinal Engineering designed a solution to these problems. Based on Cardinal's analysis, it was determined that adding area inlets and pipes along Frank and Hughbert Streets and installing a grass-lined swale at 115 West Hughbert Street to more efficiently collect stormwater runoff and direct it to the existing stormwater system along Jones Avenue was the most cost effective way to address the drainage and safety concerns reported by the citizens.

On March 24, 2020, City Council approved Contract K-1920-78 between the City of Norman and EMC Services, LLC, for furnishing of all labor and materials for the Frank and Hughbert Streets Drainage Improvements Project for an amount of $78,577. Construction activities associated with the Frank and Hughbert Streets Drainage Improvement Project were completed in June 2020.

DISCUSSION: This project was funded in the FYE 2020 Capital Fund. Total project costs for construction activities included installation of new stormwater pipes and area inlets along Frank and Hughbert Streets and relocation of water service lines on Frank Street. The total actual project cost is $93,238.85.

Change Order No. 1 to Contract K-1920-78 with EMC...

Click here for full text