Title: CONSIDERATION OF A PRELIMINARY PLAT FOR ONCUE #138 ADDITION. (GENERALLY LOCATED AT THE NORTHWEST CORNER OF 24TH AVENUE S.W. AND LINDSEY STREET)
Attachments: 1. City Council Staff Report, 2. Traffic Table, 3. Location Map, 4. Preliminary Plat 012820, 5. Site Plan 012820, 6. Staff Report, 7. Transportation Impacts, 8. Predevelopment Summary ONCUE, 9. 2-13-20 PC Minutes - OnCue Prelim Plat
title
CONSIDERATION OF A PRELIMINARY PLAT FOR ONCUE #138 ADDITION. (GENERALLY LOCATED AT THE NORTHWEST CORNER OF 24TH AVENUE S.W. AND LINDSEY STREET)

Body
BACKGROUND: This item is a preliminary plat for ONCUE #138 Addition located at the northwest corner of the intersection of West Lindsey Street and 24th Avenue N.W. This property contains 2.3 acres and is proposed for commercial development with one (1) lot. The design indicates an OnCue fueling station and convenience store.

Planning Commission, at its meeting of February 13, 2020, recommended to City Council approval of the preliminary plat for ONCUE #138 Addition.

DISCUSSION: The proposed convenience store with 20 fueling stations in this addition is expected to generate approximately 3,581 trips per day, 224 AM peak hour trips, and 297 PM peak hour trips. Traffic capacities on both 24th Avenue SW and Lindsey Street exceed the demand for existing and proposed trips as a result of this development. No negative traffic impacts are anticipated. (see attached traffic table)

Being above the threshold for when a traffic impact study is required, Traffic Engineering Consultants, Inc., submitted a traffic impact study in September 2018. The development will feature a total of three access points-two full access points will be located along Springer Drive and one right-in/right-out access will be located along 24th Avenue SW. Some widening will occur along 24th Avenue SW in order to provide an exclusive left-turn lane for northbound traffic to access Springer Drive. No additional off-site improvements are required. The applicant is responsible to fund and construct all improvements along 24th Avenue SW.

PUBLIC IMPROVEMENTS:

1. Alley. Alleys are not required on lots greater than one (1) acre if sufficient circulation is provided. The proposed site plan shows proper circulation for delivery trucks and sanitation vehicles.

2. Fire Hydrants. A fire hydrant will be installed in accordance with approved ...