File #: K-1718-120Final    Version: 1 Name: Westwood Tennis Indoor Construction Final Payment
Type: Contract Status: Passed
File created: 5/28/2019 In control: City Council
On agenda: 6/11/2019 Final action: 6/11/2019
Title: FINAL ACCEPTANCE AND FINAL PAYMENT OF CONTRACT K-1718-120 BY AND BETWEEN THE NORMAN MUNICIPAL AUTHORITY AND FLINTCO, L.L.C., FOR THE WESTWOOD TENNIS CENTER INDOOR COURT FACILITY CONSTRUCTION PROJECT.
Attachments: 1. Text File, 2. Photograph Tennis Center, 3. PO-Flintco

Title

FINAL ACCEPTANCE AND FINAL PAYMENT OF CONTRACT K-1718-120 BY AND BETWEEN THE NORMAN MUNICIPAL AUTHORITY AND FLINTCO, L.L.C., FOR THE WESTWOOD TENNIS CENTER INDOOR COURT FACILITY CONSTRUCTION PROJECT.

 

Body

BACKGROUND:   On 27 March 2018, the Norman Municipal Authority approved Contract K-1718-120 with Flintco, LLC for the Construction Management at Risk Services for the Westwood Tennis Indoor Facility Project.  Subsequently, on August 23, 2018, Amendment #1 to Contract Number 1718-120 was approved for the Guaranteed Maximum Price for the project construction. Included in this project were the demolition of two outdoor courts and replacement of them with a new tensile fabric structure covering two new U.S. Tennis Association (USTA) - regulation courts.  The indoor court facility includes surfacing, drapes, court dividers, lighting, HVAC system, fire suppression system, exterior walkways and grading.

 

DISCUSSION:  The Westwood Tennis Indoor Facility Project awarded to FLINTCO, LLC (including amendment #1) was in the total amount of $1,475,395.   Monthly payments were made during the construction process.

 

All building inspections have been completed; and a certificate of occupancy was issued in May.  On 24 May, 2019, the project was determined to be complete as per specifications, and a ribbon cutting was held at the facility.

 

RECOMMENDATION:  It is recommended that City Council, acting as the Norman Municipal Authority, accept the Westwood Tennis Indoor Facility Project as complete and authorize final payment to Flintco, L.L.C., in the amount of $63,362.48.  Funding is available in Project NFB007, NORMAN FORWARD Westwood Tennis (051-9364-451.61-01) .