File #: K-1718-106 Final    Version: 1 Name: NE Lions Restroom/Pavilion Final Payment
Type: Contract Status: Passed
File created: 5/6/2019 In control: City Council
On agenda: 5/28/2019 Final action: 5/28/2019
Title: FINAL ACCEPTANCE AND FINAL PAYMENT OF CONTRACT K-1718-106: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND METRO BUILDING SERVICES FOR THE NORTHEAST LIONS RESTROOM AND PAVILION PROJECT FOR THE PARKS AND RECREATION DEPARTMENT.
Attachments: 1. Text File, 2. NE Lions's Restroom/Pavilion, 3. PO 303398

Title

FINAL ACCEPTANCE AND FINAL PAYMENT OF CONTRACT K-1718-106: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND METRO BUILDING SERVICES FOR THE NORTHEAST LIONS RESTROOM AND PAVILION PROJECT FOR THE PARKS AND RECREATION DEPARTMENT.

 

Body

BACKGROUND:  On 27 March 2018, City Council approved RFP Number 1718-43 for the Northeast Lions Restroom/Pavilion Project.  Included in this project were the replacement of the original restroom building and the addition of a new pavilion.

 

DISCUSSION:  The Northeast Lions Restroom/Pavilion Project was awarded to Metro Building Services, LLC in the amount of $147,147.30.   Partial payments were made during the construction process.

 

On 10 May 2019, all City of Norman building inspections were complete and Parks and Recreation staff inspected this project and found it to be complete as per specifications.

 

RECOMMENDATION: It is recommended the City Council accept the Northeast Lions Restroom and Pavilion Project as complete and authorize final payment in the amount of $17,559.04 to Metro Building Services.  Funding is available in Park Master Plan Projects, Construction (account 050-9218-452.61-01; Project PR0153).