File #: K-1718-9 CO#1    Version: 2 Name: Change Order No. One and Final Acceptance of 2016 Urban Asphalt Pavement Repair Bond Program FYE 2017 Locations
Type: Contract Status: Passed
File created: 12/19/2018 In control: City Council
On agenda: 1/22/2019 Final action: 1/22/2019
Title: CHANGE ORDER NO. ONE TO CONTRACT K-1718-9: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND SILVER STAR CONSTRUCTION CO, INC., DECREASING THE CONTRACT AMOUNT BY $199,470.04 FOR A REVISED CONTRACT AMOUNT OF $1,087,109.96 FOR THE 2016 URBAN ASPHALT PAVEMENT REPAIR BOND PROGRAM, FYE 2017 LOCATIONS; AND FINAL ACCEPTANCE OF THE PROJECT.
Attachments: 1. Text File, 2. Change Order, 3. Silver Star Final Pay App, 4. Map with all projects
Title
CHANGE ORDER NO. ONE TO CONTRACT K-1718-9: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND SILVER STAR CONSTRUCTION CO, INC., DECREASING THE CONTRACT AMOUNT BY $199,470.04 FOR A REVISED CONTRACT AMOUNT OF $1,087,109.96 FOR THE 2016 URBAN ASPHALT PAVEMENT REPAIR BOND PROGRAM, FYE 2017 LOCATIONS; AND FINAL ACCEPTANCE OF THE PROJECT.

Body
BACKGROUND: In the Norman General Obligation Bond Election of April 2016, voters approved the Street Maintenance Bond Program. All bond projects are to be completed in five years under the approved program budget of $25,000,000. The 2016 Street Maintenance Bond Program includes four categories as follows:

* Urban Asphalt Street Rehabilitation
* Urban Concrete Street Rehabilitation
* Rural Road Rehabilitation
* Urban Street Reconstruction

Locations throughout Norman to be maintained were determined prior to the bond election using the City's pavement management system. The pavement management system uses field data to numerically rate each street in Norman. The streets with the lowest ranking are priority to be maintained (resurfaced, concrete panels replaced, curb/gutter repaired, etc.). During each year of the 2016 Street Maintenance Bond Program, the streets that were identified for that year will be maintained. The FYE 2017 Urban Asphalt Street Rehabilitation Bond projects included 34 selected residential streets, in 11 different subdivisions located throughout the City of Norman.

DISCUSSION: The bid opening was conducted on July 20, 2017. On August 8, 2017, the City Council awarded the FYE 2017 Urban Asphalt Street Rehabilitation Bond Project to Silver Star Construction of Moore in the amount of $1,286,580.

On October 16, 2017 construction started on the FYE 2017 Urban Asphalt Street Maintenance Bond projects.

All work, including the rehabilitation of 34 selected residential streets, in 11 different subdivisions, was completed per the contract specifications. A final pay application of $54,355.52 was su...

Click here for full text