File #: K-1819-1 CO#2    Version: 1 Name: East Norman Recycling Center
Type: Contract Status: Passed
File created: 11/13/2018 In control: City Council
On agenda: 11/27/2018 Final action: 11/27/2018
Title: CHANGE ORDER NO. TWO TO CONTRACT K-1819-1: BY AND BETWEEN THE CITY OF NORMAN, THE NORMAN MUNICIPAL AUTHORITY, AND CENTRAL CONTRACTING SERVICES, INC., INCREASING THE CONTRACT AMOUNT BY $16,393.47 FOR A REVISED CONTRACT AMOUNT OF $1,563,869.47 TO COMPLETE THE RECYCLING PAD AT THE EAST NORMAN RECYCLING CENTER AS PART OF THE URBAN CONCRETE PAVEMENT STREET MAINTENANCE BOND PROGRAM CONTRACT.
Attachments: 1. Text File, 2. CO#2 Contractor Signed for NMA Meeting.pdf
Title
CHANGE ORDER NO. TWO TO CONTRACT K-1819-1: BY AND BETWEEN THE CITY OF NORMAN, THE NORMAN MUNICIPAL AUTHORITY, AND CENTRAL CONTRACTING SERVICES, INC., INCREASING THE CONTRACT AMOUNT BY $16,393.47 FOR A REVISED CONTRACT AMOUNT OF $1,563,869.47 TO COMPLETE THE RECYCLING PAD AT THE EAST NORMAN RECYCLING CENTER AS PART OF THE URBAN CONCRETE PAVEMENT STREET MAINTENANCE BOND PROGRAM CONTRACT.

Body
BACKGROUND: In the summer of 2013, the Sanitation Division of the Norman Municipal Authority (NMA) established an East Norman Recycling Center in the parking lot of Fire Station #9 located at 3001 East Alameda. During construction of the East Norman Library, the recycling center was temporarily closed to reduce traffic within the site.

Once the library construction was complete, staff worked to expedite completion of a new paved area for the recycling center by utilizing the unit prices bid under the Urban Concrete Pavement Street Maintenance Bond Program contract under the Public Works Department. Contract K-1819-1 with Central Contracting Services, Inc. was approved on July 24, 2018, in the amount of $1,451,515. Change Order No. 1 to Contract K-1819-1, also approved July 24, 2018, increased the contract amount by $95,961 to allow the paving for the recycling center to be constructed as part of the project. The concrete installed under the change order was 9 inches thick making it suitable for the large trucks accessing the recycling center.

DISCUSSION: Dirt work to level and compact the area of the recycling center began September 18 and was completed October 4, 2018. Concrete placement began October 8 and was complete November 5, 2018; a retaining wall was required to the south in order to create a relatively level site. As shown in the attached aerial, the new recycling center is located behind the East Norman Library towards the north end of the property. The paved area for the recycling center is complete and final inspection was performed November 6, 2018 ...

Click here for full text