File #: K-1011-148 AMD #4    Version: 1 Name: Garver Amendment #4 additional services
Type: Contract Status: Passed
File created: 10/15/2018 In control: City Council
On agenda: 11/13/2018 Final action: 11/13/2018
Title: AMENDMENT NO. FOUR TO CONTRACT K-1011-148: BY AND BETWEEN THE NORMAN UTILITIES AUTHORITY AND GARVER, L.L.C., INCREASING THE CONTRACT AMOUNT BY $89,300 FOR A REVISED CONTRACT AMOUNT OF $5,193,200 TO PROVIDE ADDITIONAL CONSTRUCTION ADMINISTRATION, CONSTRUCTION OBSERVATION, AND WARRANTY ASSISTANCE SERVICES FOR THE WRF PHASE 2 IMPROVEMENTS AND THE WRF PHASE 2 MAINTENANCE ADDITIONS.
Attachments: 1. Text File, 2. Amendment 4, Garver signed, 3. Amendment 4, Garver Requisition, 4. Master
Title
AMENDMENT NO. FOUR TO CONTRACT K-1011-148: BY AND BETWEEN THE NORMAN UTILITIES AUTHORITY AND GARVER, L.L.C., INCREASING THE CONTRACT AMOUNT BY $89,300 FOR A REVISED CONTRACT AMOUNT OF $5,193,200 TO PROVIDE ADDITIONAL CONSTRUCTION ADMINISTRATION, CONSTRUCTION OBSERVATION, AND WARRANTY ASSISTANCE SERVICES FOR THE WRF PHASE 2 IMPROVEMENTS AND THE WRF PHASE 2 MAINTENANCE ADDITIONS.

Body
BACKGROUND: The Wastewater Master Plan (WWMP), adopted by the Norman Utilities Authority (NUA) in 2001, recommended that additional facilities treating an average design flow (ADF) of 21.5 million gallons per day (MGD) would ultimately be needed to serve the area approved for urban development under the 2025 Land Use and Transportation Plan. The WWMP recommended expansion of the South Water Reclamation Facility (WRF) from 12 to 17 MGD and construction of a new North WRF with an ultimate ADF of 4.5 MGD.

More recently, staff recommended and the NUA agreed that the South WRF would be rehabilitated and expanded first and the North WRF would be designed and constructed in the future when the capacity of the recently expanded Lift Station D was consumed. Based on this premise, Norman voters approved a rate increase in October 2013, in part for expanded treatment capacity at the South WRF.

Regulatory Requirements: Our Oklahoma Pollutant Discharge Elimination System (OPDES) permit for the South WRF issued by Oklahoma Department of Environmental Quality (DEQ), required construction of new disinfection facilities and compliance with final discharge limits by July 1, 2013. On September 12, 2014, the NUA and DEQ agreed to Consent Order 13-077 which included the following schedule:

1. Complete construction of disinfection facilities by January 1, 2016;
2. Attain compliance with final limits for Fecal Coliform by July 1, 2016;
3. Complete construction of all facilities by January 1, 2017;
4. Attain compliance with final limits for Total Suspended Solids by July 1, 2017.

The NUA comple...

Click here for full text