File #: K-1718-90 CO# 2    Version: 1 Name: Final Change Order to Contract for Sidewalk Horizontal Saw Cutting Project
Type: Contract Status: Passed
File created: 8/7/2018 In control: City Council
On agenda: 9/11/2018 Final action: 9/11/2018
Title: CHANGE ORDER NO. TWO TO CONTRACT K-1718-90: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND PRECISION CONCRETE CUTTING OF OKLAHOMA, L.L.C., INCREASING THE CONTRACT AMOUNT BY $440.77 FOR A REVISED CONTRACT AMOUNT OF $40,440.77 FOR THE CITY SIDEWALK HORIZONTAL SAW CUTTING PROJECT, FINAL ACCEPTANCE OF THE PROJECT, AND BUDGET TRANSFER BETWEEN PROJECT ACCOUNTS.
Attachments: 1. Text File, 2. Change Order, 3. Sidewalk-Saw Cutting Project Area, 4. K-1718-90_Invoice

Title

CHANGE ORDER NO. TWO TO CONTRACT K-1718-90:  BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND PRECISION CONCRETE CUTTING OF OKLAHOMA, L.L.C., INCREASING THE CONTRACT AMOUNT BY $440.77 FOR A REVISED CONTRACT AMOUNT OF $40,440.77 FOR THE CITY SIDEWALK HORIZONTAL SAW CUTTING PROJECT, FINAL ACCEPTANCE OF THE PROJECT, AND BUDGET TRANSFER BETWEEN PROJECT ACCOUNTS.

 

Body

BACKGROUNDOn February 27, 2018, City Council approved the contract and Change Order No. 1 to fund the Sidewalk Horizontal Saw Cutting Project by Precision Concrete Cutting of Oklahoma, LLC. in the amount of $40,000.

 

The target area for this project was bounded by Boyd Street on the north, Lindsey Street on the south; Pickard Avenue on the west; College Avenue from Boyd Street to Brooks Street; Elm Avenue from Brooks Street to Lindsey Street on the east; and both sides of Brooks Street between College Avenue and Elm Avenue.

 

Work began in April of 2018, and the project was completed May 18th, 2018.

 

DISCUSSIONPrecision Concrete Cutting of Oklahoma, LLC successfully completed the work in the targeted area with a retainage payable amount of $1,581.26, based on field observations. Precision Concrete Cutting was directed to make repairs in an adjacent location on the west side of Pickard Avenue for the additional 11.9 inch/feet of sawing, with an additional cost of $440.77.

 

RECOMMENDATION NO. 1Staff is recommending approval of Change Order No. 2 to increase the project amount to by $440.77 for a total of $40,440.77; an increase of 1.1%. Funding for the Change Order is available by transfer from the unencumbered Citywide Sidewalk Reconstruction Program, Construction (account 050-9052-431.61-01; project TC0273) to Sidewalk Horizontal Saw Cutting Project, Construction (account 050-9407-431.61-01), in the amount of $440.77. 

 

RECOMMENDATION NO. 2Staff further recommends acceptance of the Sidewalk Horizontal Saw Cutting Project and authorization of final payment in the amount of $2,022.03 (from Construction account 050-9407-431.61-01; Project Number TC0155).