File #: K-1314-136 CO#6    Version: 1 Name: Final CO and acceptance of WRF Phase 2 Improvements
Type: Contract Status: Passed
File created: 8/21/2018 In control: City Council
On agenda: 9/11/2018 Final action: 9/11/2018
Title: CHANGE ORDER NO. SIX (FINAL) TO CONTRACT K-1314-136: BY AND BETWEEN THE NORMAN UTILITIES AUTHORITY AND ARCHER WESTERN CONSTRUCTION, L.L.C. DECREASING THE CONTRACT AMOUNT BY $72,545.83 FOR A REVISED CONTRACT AMOUNT OF $52,154,160.17 AND ADDING 61 CALENDAR DAYS TO THE CONTRACT FOR THE WATER RECLAMATION FACILITY PHASE 2 IMPROVEMENTS AND FINAL ACCEPTANCE OF THE PROJECT.
Attachments: 1. Change Order, 2. CO#6 backup, 3. Release of Claimants, 4. Consent of Surety to Final Payment
Title
CHANGE ORDER NO. SIX (FINAL) TO CONTRACT K-1314-136: BY AND BETWEEN THE NORMAN UTILITIES AUTHORITY AND ARCHER WESTERN CONSTRUCTION, L.L.C. DECREASING THE CONTRACT AMOUNT BY $72,545.83 FOR A REVISED CONTRACT AMOUNT OF $52,154,160.17 AND ADDING 61 CALENDAR DAYS TO THE CONTRACT FOR THE WATER RECLAMATION FACILITY PHASE 2 IMPROVEMENTS AND FINAL ACCEPTANCE OF THE PROJECT.

Body
BACKGROUND: The Wastewater Master Plan (WWMP), adopted by the Norman Utilities Authority (NUA) in 2001, recommended that additional facilities treating an average design flow (ADF) of 21.5 million gallons per day (MGD) would ultimately be needed to serve the area approved for urban development under the City's 2025 Land Use and Transportation Plan. The WWMP recommended expansion of the South Water Reclamation Facility (WRF) from 12 to 17 MGD and construction of a new North WRF with an ultimate ADF of 4.5 MGD.

More recently, staff recommended and the NUA agreed that the South WRF would be rehabilitated and expanded first and the North WRF would be designed and constructed in the future when the sewerage conveyance capacity of the expanded Lift Station D was consumed. Based on this premise, Norman voters approved a rate increase in October 2013, in part for expanded treatment capacity at the South WRF.

Regulatory Requirements: Our Oklahoma Pollutant Discharge Elimination System (OPDES) permit for the South WRF issued by the Oklahoma Department of Environmental Quality (DEQ), required construction of new disinfection facilities and compliance with final discharge limits by July 1, 2013. On September 12, 2014, the NUA and DEQ agreed to Consent Order 13-077 which included the following schedule:
1. Complete construction of disinfection facilities by January 1, 2016;
2. Attain compliance with final limits for Fecal Coliform by July 1, 2016;
3. Complete construction of all facilities by January 1, 2017;
4. Attain compliance with final limits for Total Suspended Solids by July 1, 2017.

The N...