File #: RPT-1718-65    Version: 1 Name: City Manager's Change Order Report
Type: Communication or Report Status: Passed
File created: 5/2/2018 In control: City Council
On agenda: 5/8/2018 Final action: 5/8/2018
Title: SUBMISSION AND ACKNOWLEDGING RECEIPT OF THE CITY MANAGER'S CHANGE ORDER REPORT AND DIRECTING THE FILING THEREOF.
Attachments: 1. Text File, 2. Change Order 5 - Norman Public Library East - Signed.pdf, 3. Change Order 6 - Norman Public Library Central- Signed_.pdf
Title
SUBMISSION AND ACKNOWLEDGING RECEIPT OF THE CITY MANAGER'S CHANGE ORDER REPORT AND DIRECTING THE FILING THEREOF.

Body
INFORMATION: City Council, in its meeting of November, 8, 2011, adopted Resolution R-1112-55 delegating administrative authority to the City Manager or his designee, at his discretion, to approve change order requests that result in adjustments up to forty thousand dollars ($40,000) or 10% of any contract, whichever is less. The resolution also required that the administrative approvals of change orders be reported to the City Council with the City Manager's Weekly Report at the next regularly scheduled Council meeting and then filed with the original contract in the permanent records of the City Clerk.

Contract K-1617-68 with Globe Construction Company for the East Branch Library Project in the amount of $3,654,500 was approved by City Council on February 28, 2017.

The first four change orders are as follows:
* Change Order No. One in the amount of $7,588.12 was approved by the City Manager on August 24, 2017, providing additional drilling, concrete, reinforcement, and labor to install piers to additional depth as recorded by the engineer for the project and adding seven (7) calendar days to the contract.
* Change Order No. Two in the amount of $7,814.35 was approved by the City Manager on August 29, 2017, adding a Bent Plate at Window Heads; relocating electrical devices for more flexibility; adding Foreman Lockers and electrical in the AMH Room; and adding five (5) calendar days to the contract.
* Change Order No. Three was approved by the City Manager on October 19, 2017, increasing the contract by $3,648.20 and adding six (6) additional weather days. The work for this change order is due to obstructions in the light monitor opening in the ceiling of the building.
* Change Order No. Four was approved by the City Manager on January 15, 2018, increasing the contract by $34,126.26 and adding eight (8) calendar days. This change o...