File #: FP-1516-13    Version: 1 Name: Final Plat for Highland Village Addition, Section 9
Type: Final Plat Status: Passed
File created: 10/7/2015 In control: City Council
On agenda: 10/27/2015 Final action: 10/27/2015
Title: CONSIDERATION OF A FINAL PLAT FOR HIGHLAND VILLAGE ADDITION, SECTION 9, AND ACCEPTANCE OF PUBLIC DEDICATIONS CONTAINED THEREIN. (GENERALLY LOCATED ONE-QUARTER MILE SOUTH OF TECUMSEH ROAD AND ONE-QUARTER MILE WEST OF PORTER AVENUE)
Attachments: 1. Text File, 2. Location map, 3. Final Plat, 4. Revised Preliminary Plat, 5. Staff Report, 6. application
title
CONSIDERATION OF A FINAL PLAT FOR HIGHLAND VILLAGE ADDITION, SECTION 9, AND ACCEPTANCE OF PUBLIC DEDICATIONS CONTAINED THEREIN. (GENERALLY LOCATED ONE-QUARTER MILE SOUTH OF TECUMSEH ROAD AND ONE-QUARTER MILE WEST OF PORTER AVENUE)

body
BACKGROUND: This item is a final plat for Highland Village Addition, Section 9, and is generally located one-quarter of a mile south of Tecumseh Road and one-quarter of a mile west of Porter Avenue.

City Council, at its meeting of September 28, 2004 adopted Ordinance O-0405-6 placing this property in R-1, Single Family Dwelling District and removing it from A-2, Rural Agricultural District. City Council approved a revised preliminary plat at its meeting of February 23, 2010. The City Development Committee, at its meeting of October 9, 2015, reviewed and approved the program of public improvements and final plat for Highland Village Addition, Section 9, and recommended that the final plat be submitted to City Council for consideration.

This property consists of 11.98 acres and thirty-seven (37) single-family residential lots. There are thirty-two (32) single-family lots remaining within the subdivision. The final plats of Highland Village Additions, Sections 1 through 8 consist of 322 lots. The entire development will consist of a total of 391 single- family residential lots.

DISCUSSION: Public improvements consist of water mains with fire hydrants, sanitary sewer, drainage, street paving and sidewalk improvements. Public improvements are under construction. Park land dedication requirements have been fulfilled.

STAFF RECOMMENDATIONS: The final plat is consistent with the preliminary plat. Based upon the above information, Staff recommends approval of the final plat, acceptance of the public dedication contained therein, and authorize the Mayor to sign the final plat, subdivision bonds/cash sureties and maintenance bonds for Highland Village Addition, Section 9, subject to completion and the City Deve...

Click here for full text