File #: K-1819-128 AMD#1    Version: 1 Name: Amendment No. 1 to Contract for 24th Avenue East Widening from Lindsey to Alameda, Phase 1
Type: Contract Status: Passed
File created: 8/21/2019 In control: City Council
On agenda: 9/10/2019 Final action: 9/10/2019
Title: AMENDMENT NO. ONE TO CONTRACT K-1819-128: A PROJECT AGREEMENT BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND THE OKLAHOMA DEPARTMENT OF TRANSPORTATION INCREASING THE CONTRACT AMOUNT BY $94,304.60 FOR A REVISED CONTRACT AMOUNT OF $974,304.60 FOR THE CITY'S LOCAL SHARE FOR PROJECT STP-214B(068), STATE JOB 29300(04) FOR THE CONSTRUCTION OF 24TH AVENUE FROM LINDSEY STREET TO ALAMEDA STREET, PHASE 1, (2 TO 4 LANES) WITH SIGNALS AND ADOPTION OF RESOLUTION R-1920-29.
Attachments: 1. Staff Report, 2. Location Map, 3. Contract Amendment #1 (Revised Cap), 4. R-1920-29, 5. CONSTRUCTION Invoice(Revised from Bid), 6. Requisition
Title
AMENDMENT NO. ONE TO CONTRACT K-1819-128: A PROJECT AGREEMENT BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND THE OKLAHOMA DEPARTMENT OF TRANSPORTATION INCREASING THE CONTRACT AMOUNT BY $94,304.60 FOR A REVISED CONTRACT AMOUNT OF $974,304.60 FOR THE CITY'S LOCAL SHARE FOR PROJECT STP-214B(068), STATE JOB 29300(04) FOR THE CONSTRUCTION OF 24TH AVENUE FROM LINDSEY STREET TO ALAMEDA STREET, PHASE 1, (2 TO 4 LANES) WITH SIGNALS AND ADOPTION OF RESOLUTION R-1920-29.

Body
BACKGROUND: On November 22, 2011, the Norman City Council approved Programming Resolution R-1112-62, requesting federal funds for the 24th Avenue East Bond Project. This resolution states the City's commitment to adhere to the terms and conditions of a federally funded project including engineering design, acquisition of all necessary rights-of-way and relocation of utilities and encroachments at 100% the City's cost. In return, the Association of Central Oklahoma Governments (ACOG), through the Oklahoma Department of Transportation (ODOT), agrees to provide 80% of the construction cost and administration of the construction with the matching share from the City of Norman.

On August 28, 2012, the citizens of Norman voted in favor of a Bond Issue to finance the local share of eight transportation/stormwater improvement projects. One of the eight 2012 bond projects is the 24th Avenue East Bond Project (please see the attached location map showing the project boundaries). The total estimated project cost including design, utility relocations, right-of-way, construction and construction management is $15,388,000. The City's share is estimated to be $7,518,000.

Proposed improvements for the 24th Avenue East Bond Project include:

* Widen two miles of roadway from two lanes to four lanes;
* Intersection improvements at 24th Avenue East/Meadowood Boulevard and 24th Avenue East /Robinson Street;
* Interconnect traffic signals on 24th Avenue East from Lindsey Street to Robinson Street;
* Cont...