title
CHANGE ORDER NO. ONE TO CONTRACT NO. K-1213-47: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA AND SUN CONSTRUCTION SERVICES, L.L.C., INCREASING THE CONTRACT BY $1,308.60 FOR A REVISED CONTRACT AMOUNT OF $78,864.60 FOR THE BUILDING "A" RENOVATION PROJECT, PHASE 2, AND FINAL ACCEPTANCE OF THE PROJECT.
body
BACKGROUND: Building A on the City Hall campus was constructed in 1978 and currently houses the following two city departments including 61 employees: (1) Planning and Community Development and (2) Public Works. Improvements made to the building since it was originally constructed include roof repair and HVAC replacement. The building did not meet current accessibility standards of the Americans with Disabilities Act (ADA). In addition, customer service and public meetings were compromised due to a lack of adequate space. Employees were cramped in small working spaces. The original carpet (34 years old) still remained in the building. Many of the customers of this building are developers, builders, business and property owners. Regular meetings in the building include Pre-Development, Flood Plain Permit Committee, Greenbelt Commission, Board of Zoning Appeals, Board of Adjustment, Historic District Commission and Reapportionment Commission.
The Building A Renovations in 2011/2012 were constructed in two phases to accommodate Capital Fund budget limitations. In addition, service to the City's customers was never allowed to be interrupted. The project eventually fulfilled all needs including ADA accessibility, space utilization and customer service enhancements. The project was designed and administered by The McKinney Partnership Architects.
Bid documents and specifications for the Building A Renovation Project, Phase 2, were advertised according to State Law. Seven (7) potential bidders acquired plans and specifications and four (4) bids were received on August 17, 2012.
The low bidder was Sun Construction Services, LLC, Noble, Ok...