Title: CHANGE ORDER NO. SIX TO CONTRACT K-1516-80: BY AND BETWEEN THE NORMAN UTILITIES AUTHORITY AND CENTRAL CONTRACTING SERVICES, INC. INCREASING THE CONTRACT AMOUNT BY $76,126.54 FOR A REVISED CONTRACT AMOUNT OF $3,437,546.54 AND ADDING 59 CALENDAR DAYS TO THE CONTRACT FOR THE BERRY ROAD WATER LINE REPLACEMENT PROJECT, PHASE 3, FINAL ACCEPTANCE OF THE PROJECT, AND BUDGET TRANSFERS BETWEEN PROJECT ACCOUNTS.
Attachments: 1. Text File CO K-1516-80, 2. Location map, 3. CO#6 signed 122017, 4. CO#6 Requisition
Title
CHANGE ORDER NO. SIX TO CONTRACT K-1516-80: BY AND BETWEEN THE NORMAN UTILITIES AUTHORITY AND CENTRAL CONTRACTING SERVICES, INC. INCREASING THE CONTRACT AMOUNT BY $76,126.54 FOR A REVISED CONTRACT AMOUNT OF $3,437,546.54 AND ADDING 59 CALENDAR DAYS TO THE CONTRACT FOR THE BERRY ROAD WATER LINE REPLACEMENT PROJECT, PHASE 3, FINAL ACCEPTANCE OF THE PROJECT, AND BUDGET TRANSFERS BETWEEN PROJECT ACCOUNTS.

Body
BACKGROUND: The Berry Waterline Replacement project (WA0305) was expected to include about 11,000 linear feet (LF) of 16-inch waterline along the west side of Berry Road from Robinson to Lindsey and approximately 3,000 LF of 24-inch waterline east along Lindsey from Berry to Chautauqua.

On May 10, 2011, the NUA approved Amendment No. 1 to Contract K-0910-61 in the amount of $172,000 authorizing Poe & Associates (Poe) to perform surveying, design and limited construction management services for the Berry Waterline Replacement project.

On March 10, 2015, the NUA approved Contract K-1415-70 in the amount of $1,334,675 with Central Contracting Services, Inc. for the construction of the Berry Road Waterline Replacement, Phase 1. The Phase 1 project included the 24-inch line along Lindsey from Berry to Chautauqua. The Phase 1 construction was complete on August 24, 2015 at a cost of $1,334,675.

On September 22, 2015, the NUA approved Contract K-1516-43 with McKee Utility Contractors, Inc. in the amount of $1,206,023.50 for the construction of the Berry Road Waterline Replacement, Phase 2. The Phase 2 project included the 16-inch waterline from just north of Lindsey to just north of Main Street. On January 26, 2016, the NUA and the City of Norman (City) approved Amendment No. 1 including the City of Norman as a party to the contract and also approved Change Order No. 1 (CO#1) to include road repairs to the western lane of Berry Road. CO#1 increased the contract amount by $410,205 for a revised contract amount of $1,616,228.50. The Phase 2 construction was...