File #: K-1516-80 CO#5    Version: 1 Name: Water Line Segment D, Phase IV
Type: Contract Status: Passed
File created: 5/10/2017 In control: City Council
On agenda: 5/23/2017 Final action: 5/23/2017
Title: CHANGE ORDER NO. FIVE TO CONTRACT K-1516-80: WITH CENTRAL CONTRACTING SERVICES, INC. INCREASING THE CONTRACT AMOUNT BY $777,235 FOR A REVISED CONTRACT AMOUNT OF $3,361,420 AND ADDING 84 CALENDAR DAYS TO THE CONTRACT TO INCLUDE INSTALLATION OF THE CHAUTAUQUA WATER LINE BETWEEN LINDSEY STREET AND TIMBERDELL AVENUE AS PART OF THE BERRY ROAD WATERLINE REPLACEMENT PROJECT, PHASE 3.
Attachments: 1. Text File CO Central, 2. Location Map, 3. Berry Road 3 WL CO#5 signed, 4. NUA PR, 5. CON PR
Title
CHANGE ORDER NO. FIVE TO CONTRACT K-1516-80: WITH CENTRAL CONTRACTING SERVICES, INC. INCREASING THE CONTRACT AMOUNT BY $777,235 FOR A REVISED CONTRACT AMOUNT OF $3,361,420 AND ADDING 84 CALENDAR DAYS TO THE CONTRACT TO INCLUDE INSTALLATION OF THE CHAUTAUQUA WATER LINE BETWEEN LINDSEY STREET AND TIMBERDELL AVENUE AS PART OF THE BERRY ROAD WATERLINE REPLACEMENT PROJECT, PHASE 3.

Body
BACKGROUND: The Berry Waterline Replacement project (WA/WB0305) was expected to include about 11,000 linear feet (LF) of 16-inch waterline along the west side of Berry Road from Robinson to Lindsey and approximately 3,000 LF of 24-inch waterline east along Lindsey from Berry to Chautauqua where it will connect to the existing 16-inch Lindsey Waterline project completed in 2005.

On May 10, 2011, the NUA approved Amendment No. 1 to Contract K-0910-61 in the amount of $172,000 authorizing Poe & Associates (Poe) to perform surveying, design and limited construction management services for the Berry Waterline Replacement project.

On March 10, 2015, the NUA approved Contract K-1415-70 in the amount of $1,334,675 with Central Contracting Services, Inc. for the construction of the Berry Road Waterline Replacement, Phase 1. The Phase 1 project included the 24-inch line along Lindsey from Berry to Chautauqua as a continuation of the Segment D Waterline. The Phase 1 construction was complete on August 24, 2015 at a cost of $1,334,675.

On September 22, 2015, the NUA approved Contract K-1516-43 with McKee Utility Contractors, Inc. in the amount of $1,206,023.50 for the construction of the Berry Road Waterline Replacement, Phase 2. The Phase 2 project includes the 16-inch waterline from Avondale to just north of Main Street. On January 26, 2016, the NUA and the City of Norman (City) approved Amendment No. 1 to the contract including the City as a party to the contract and also approved Change Order No. 1 (CO#1) expanding road repairs to the full west lane of Berry Road; CO#1 increased t...