File #: K-1516-62 Final    Version: 1 Name: Final Acceptance of he Trails in Three Parks Project
Type: Contract Status: Passed
File created: 1/29/2016 In control: City Council
On agenda: 2/9/2016 Final action: 2/9/2016
Title: FINAL ACCEPTANCE AND FINAL PAYMENT OF CONTRACT K-1516-62: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND TEXOMA PAVING AND CONSTRUCTION, L.C.C. FOR THE WALKING TRAILS IN THREE PARKS CONSTRUCTION PROJECT. (LION'S MEMORIAL PARK, COLONIAL ESTATES PARK AND OAK TREE SOUTH PARK)
Attachments: 1. Text File Final Acceptance, 2. Texoma P.O., 3. Colonial Estates Park Trail, 4. Oak Tree Before

Title

FINAL ACCEPTANCE AND FINAL PAYMENT OF CONTRACT K-1516-62: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND TEXOMA PAVING AND CONSTRUCTION, L.C.C. FOR THE WALKING TRAILS IN THREE PARKS CONSTRUCTION PROJECT. (LION’S MEMORIAL PARK, COLONIAL ESTATES PARK AND OAK TREE SOUTH PARK)

 

Body

BACKGROUND:  On 27 October 2015, City Council approved RFP Number 1516-16 for the Walking Trails in Three Parks Project.   This project included replacing the existing gravel walking trails in Lions Memorial, Colonial Estates and Oak Tree South Parks with a six foot wide concrete walking trail and repairs or additions, as needed, to the existing sidewalks in order to make a complete, accessible walking route through and around each park.  This project was funded by Parkland Development Fees collected for each park.  Contract Number K-1516-62 was awarded to Texoma Paving and Construction in the amount of $136,665.  Funding for the project was available in the following construction accounts:

 

Project PR0163, Oak Tree South Park Improvements (052-9100-452.61-01) - $40,160

Project PR0136, Colonial Estates Park Improvements (#052-9059-452.61-01) - $42,195

Project PR0161, Lions Memorial Park Improvements (#052-9213-452.61-01) - $43,404

Project PR0254, Lions Memorial Park Improvements (#052-7042-452.61-01) - $10,906

 

DISCUSSION:  The Walking Trails in Three Parks Project proceeded on schedule and partial payments were made throughout the construction. 

 

On 20 January 2016, staff made the final inspection, found the project to be complete as per specifications and recommends that City Council accept the project as complete and authorize final payment.

 

RECOMMENDATION:  It is recommended that City Council accept the Walking Trails in Three Parks Project as complete and authorize final payment in the amount of $8,633.25 to Texoma Paving and Construction, LLC.