File #: K-1415-144 Final    Version: 1 Name: Final Acceptance Santa Fe Depot Sewer Line Project
Type: Contract Status: Passed
File created: 7/22/2015 In control: City Council
On agenda: 8/11/2015 Final action: 8/11/2015
Title: FINAL ACCEPTANCE AND FINAL PAYMENT OF CONTRACT K-1415-144: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND URBAN CONTRACTORS, L.L.C., FOR THE SANTA FE DEPOT SEWER LINE REPAIR PROJECT.
Attachments: 1. Text File Santa Fe Final, 2. Urban Contractors PO

Title

FINAL ACCEPTANCE AND FINAL PAYMENT OF CONTRACT K-1415-144:  BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND URBAN CONTRACTORS, L.L.C., FOR THE SANTA FE DEPOT SEWER LINE REPAIR PROJECT.

 

Body

BACKGROUND:  On 23 June 2015, City Council approved Contract K-1415-144 with Urban Contractors, LLC in the amount of $38,325 for the Santa Fe Depot Sewer Line Repair Project.  This project was requested due to the failure of the sewer line and repeated back-ups into the building’s basement.  This project included the replacement of the sewer line from the Depot building to the sewer main and the installation of a sump pump and associated plumbing.

 

DISCUSSION:   The Santa Fe Depot Sewer Line Repair Project was completed on 15 July 2015 and inspected by City staff.  A partial payment was forwarded for processing on 22 July 2015.

 

RECOMMENDATION:  It is recommended that City Council accept this project as complete and authorize final payment in the amount of $1,916.25 to Urban Contractors, L.L.C.  Funding is available in Depot Sewer Line Repair, Construction (account 050-9677-419.61-01; project EF0201).