File #: K-1920-12 CO#1    Version: 1 Name: CO#1 & Final Acceptance McCall Dr. Reconstruction
Type: Contract Status: Passed
File created: 3/24/2020 In control: City Council
On agenda: 4/14/2020 Final action: 4/14/2020
Title: CHANGE ORDER NO. ONE TO CONTRACT K-1920-12: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND NASH CONSTRUCTION COMPANY, INC. INCREASING THE CONTRACT AMOUNT BY $6,994.94 FOR A REVISED CONTRACT AMOUNT OF $474,051.69 AND FINAL ACCEPTANCE OF THE PROJECT.
Attachments: 1. City Council Staff Report, 2. K-1920-12 Change Order No. 1, 3. Cost Summary Table, 4. Location Map
Title
CHANGE ORDER NO. ONE TO CONTRACT K-1920-12: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND NASH CONSTRUCTION COMPANY, INC. INCREASING THE CONTRACT AMOUNT BY $6,994.94 FOR A REVISED CONTRACT AMOUNT OF $474,051.69 AND FINAL ACCEPTANCE OF THE PROJECT.

Body
BACKGROUND: In the Norman General Obligation Bond Election of 2016, voters approved the Street Maintenance Bond Program, a 5-year, 4-phase program to address maintenance needs on neighborhood streets. The four categories include (1) Urban Asphalt Street Rehabilitation, (2) Urban Concrete Street Rehabilitation, (3) Urban Road Reconstruction and (4) Rural Road Rehabilitation. Prior to the election, the City provided a list of all streets included in the program based upon the pavement condition data from the City's current Pavement Management System. The following is the list of Road Reconstruction projects included in the 2016 GOB Election:

2017 - Lahoma Street - Gray Street to Nebraska Street
2018 - Lahoma Street - Nebraska Street to Hughbert Street
2019 - Walnut Road - South 2700 Block to Imhoff Road
2020 - McCall Drive - Chautauqua Avenue to Pickard Avenue
2021 - Pickard Avenue - Kansas Street to Acres Street

McCall Drive is located in an established residential neighborhood. The current roadway is constructed of concrete pavement with curb and gutter. The concrete pavement is in poor condition, and the substructure has failed in several locations along the 0.50 lane-mile stretch of the roadway. The reconstruction project involves removal of the existing pavement and curb and gutter, stabilizing the subgrade, placing new concrete pavement and bringing adjacent driveways into compliance with Americans with Disabilities Act guidelines.

On August 27, 2019, City Council awarded the Street Maintenance Bond Reconstruction Project - McCall Drive from Chautauqua Avenue to Pickard Avenue, Contract K-1920-12 to Nash Construction Company, Inc. of Oklahoma City In the amount of $467,056.75.

DISCUSSION: ...