Title
CHANGE ORDER NO. ONE TO CONTRACT K-1718-88: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA AND RDNJ, L.L.C. DBA A-TECH PAVING OF EDMOND, OKLAHOMA, DECREASING THE CONTRACT AMOUNT BY $42,851.49 FOR A REVISED CONTRACT AMOUNT OF $334,545.51 FOR THE LAHOMA AVENUE FROM NEBRASKA STREET TO HUGHBERT STREET RECONSTRUCTION CONTRACT, AND FINAL ACCEPTANCE OF THE PROJECT.
Body
BACKGROUND: In the Norman General Obligation Bond Election of 2016, voters approved the Street Maintenance Bond Program, a 5-year, 4-phase program to address maintenance needs on neighborhood streets. The four categories include (1) Urban Asphalt Streets Rehabilitation, (2) Urban Concrete Streets Rehabilitation, (3) Urban Streets Reconstruction and (4) Rural Road Rehabilitation. Prior to the election, the City provided a list of all streets included in the program based upon the pavement condition data from the City's current Pavement Management System. The following is the list of Urban Street Reconstruction projects included in the 2016 GOB Election:
2017 - Lahoma Avenue - Gray Street to Nebraska Street
2018 - Lahoma Avenue - Nebraska Street to Hughbert Street
2019 - Walnut Road - South 2700 Block to Imhoff Road
2020 - McCall Drive - Chautauqua Avenue to Pickard Avenue
2021 - Pickard Street - Kansas Street to Acres Street
Lahoma Street from Nebraska Street to Hughbert Street is located in the central part of Norman. The area around the project is established residential housing. The roadway was constructed of asphalt pavement with no curb and gutter. The roadway was originally constructed in the early 1940's when housing for the U.S. Navy airbase was established. The stormwater drained through ditches on either side of the roadway. The City's goal was to provide residents with a new driving surface, curbs and guttering, and improved drainage systems. Specific improvements for this project include:
* 1,370 feet of new two-lane roadway;
* 2,700 curb and gutter throughout;
* Stormwater ...