Title
CONSIDERATION OF ACCEPTANCE OF A WARRANTY DEED FROM RENEE G. AND LYNN M. SIMPSON IN THE AMOUNT OF $41,200 FOR THE FYE15 WATER WELLS/SUPPLY LINES PROJECT.
Body
BACKGROUND: On June 14, 2016, the Norman Utilities Authority (NUA) approved Contract K-1516-139 with Carollo Engineers to determine suitable new well sites situated above thick saturated sand zones; prepare a bid package for drilling test wells and recommend where the groundwater well field expansion should take place.
Carollo and NUA staff worked closely with ACOG to map the water bearing sand zones and identified 45 potential test well sites to investigate. The test well sites were prioritized and landowners were contacted to determine if they were willing to initially allow drilling of a test well and, if found suitable for potable water use, allow construction of a production well. The attached map shows the existing wells and potential new wells located in north east Norman.
On November 27, 2018 the NUA approved Contract K-1819-44 with Layne Christensen Company of Guthrie, Oklahoma in the amount of $4,714,421.72 for the drilling of the test sites as well as the production wells. $674,310 has been expended to date for test well drilling.
DISCUSSION: Results from the test holes have identified eleven (11) potential permanent well sites for the NUA to pursue. Three (3) sites will be purchased and eight (8) sites will be acquired through permanent easement. The sites will allow for the production well, well house, access drive, fencing and all associated water appurtenances to be installed so that the well is connected into the Norman water system. All landowners were offered a price of $20,000 per acre for purchase and 90% of that price for permanent easement.
The proposed warranty deed is for a square area measuring 300 feet by 300 feet which equates to 2.06 acres. The NUA offered $41,200 for the 2.06-acre property and the property owner accepted the offer. The site is located...
Click here for full text