CONSIDERATION OF AWARDING OF BID 1920-17; CONTRACT K-1920-41 BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND CENTRAL CONTRACTING SERVICES, INC., IN THE AMOUNT OF $341,839; PERFORMANCE BOND B-1920-30; STATUTORY BOND B-1920-31, AND MAINTENANCE BOND MB-1920-15 FOR THE URBAN CONCRETE PAVEMENT FYE 2020 LOCATIONS PROJECT 2 (VICKSBURG DRIVE; BILOXI DRIVE; BENTBROOK PLACE; AND INDUSTRIAL BOULEVARD; AND RESOLUTION R-1920-28 GRANTING TAX EXEMPT STATUS.
Body
BACKGROUND: In the Norman General Obligation Bond Election of 2016, voters approved the Street Maintenance Bond Program, a 5-year, 4-phase program to address maintenance needs on neighborhood streets. The four categories include (1) Urban Asphalt Street Rehabilitation, (2) Urban Concrete Street Rehabilitation, (3) Urban Road Reconstruction and (4) Rural Road Rehabilitation. Prior to the election, the City provided a list of all streets included in the program based upon the pavement condition data from the City's current Pavement Management System. The following is the list of the Street Maintenance Bond Program - Urban Concrete Pavement FYE 2020 Project 2 locations included in this Bid:
Vicksburg Avenue - Alameda Street to Beaumont Drive
Biloxi Drive - Beaumont Drive to Lindsey Street
Bentbrook Place - Parkside Road to Hearthstone Drive
Industrial Boulevard - Lexington Street to Rock Creek Road
The roadways included in this project are located in established residential and industrial areas. The current roadways are constructed of concrete pavement, which is in poor condition. This project involves rehabilitation of the existing pavement including panel replacement.
DISCUSSION: Bid documents and specifications for the Street Maintenance Bond Program - Urban Concrete Pavement FYE 2020 Locations, Project 2 were advertised on August 22, 2019 and August 29, 2019 in accordance with State Law. Four (4) bids were received on September 12, 2019.
The low bidder is Central Contracting Services, Inc. of Norman...