File #: K-1920-73 CO#2    Version: 1 Name: Pipe-Burst 1000 LF SS on Chautauqua Avenue
Type: Contract Status: Passed
File created: 5/21/2020 In control: City Council
On agenda: 6/9/2020 Final action: 6/9/2020
Title: CHANGE ORDER NO. TWO TO CONTRACT K-1920-73: BY AND BETWEEN THE NORMAN UTILITIES AUTHORITY AND HORSESHOE CONSTRUCTION, INC., INCREASING THE CONTRACT AMOUNT BY $129,564 FOR A REVISED CONTRACT AMOUNT OF $2,925,725.25 AND ADDING 20 CALENDAR DAYS TO THE CONTRACT FOR THE FYE 2017 SEWER MAINTENANCE PROJECT AND BUDGET TRANSFER BETWEEN PROJECT ACCOUNTS.
Attachments: 1. City Council Staff Report, 2. CO#2 Revised 2020-05-18, 3. Project Location Map
Title
CHANGE ORDER NO. TWO TO CONTRACT K-1920-73: BY AND BETWEEN THE NORMAN UTILITIES AUTHORITY AND HORSESHOE CONSTRUCTION, INC., INCREASING THE CONTRACT AMOUNT BY $129,564 FOR A REVISED CONTRACT AMOUNT OF $2,925,725.25 AND ADDING 20 CALENDAR DAYS TO THE CONTRACT FOR THE FYE 2017 SEWER MAINTENANCE PROJECT AND BUDGET TRANSFER BETWEEN PROJECT ACCOUNTS.

Body
BACKGROUND: In 2001, the citizens of Norman approved a five dollar per month sewer maintenance fee to provide for the systematic replacement of aged and deteriorating neighborhood sewer lines. The fiscal year 2016-2017 (FYE17) Sewer Maintenance Project (SMP17) study area is shown on the attached map. After extensive study by Norman Utilities Authority (NUA) staff of Sewer Line Maintenance Division and Utilities Engineering, the sanitary sewer lines within the study area were determined to require rehabilitation, replacement or repair due to pipes or appurtenances being in poor condition, or no action due to pipes and appurtenances being in good condition.

The SMP17 study area is generally bounded by Cavecreek Street to the north, Porter Avenue to the west, Rock Creek Road to the south, and 12th Avenue NE to the east. It will replace about 28,500 feet (about 5.7 miles) of old sewer lines and rehabilitate or replace 161 manholes. Generally, the selected contractor will install high-density polyethylene (HDPE) sewer pipe, primarily using the pipe-bursting technique. This technique allows long lengths of joint less HDPE piping to be pulled into the old pipe at manholes as it is expanded with the bursting tool. House sewer service connections are then re-connected to the new pipe; approximately 455 private residences will be affected.

Bids were opened on March 12, 2020 and Horseshoe Construction, Inc. (Horseshoe) of La Porte, Texas was the low bidder for the Base Bid at $2,796,161.25. On April 14, 2020, the NUA authorized award and approved Contract K-1920-73 with Horseshoe for $2,796,161.25. The contract t...