File #: K-1617-56    Version: 1 Name: Westwood Family Aquatic Center Project
Type: Contract Status: Passed
File created: 9/21/2016 In control: City Council
On agenda: 9/27/2016 Final action: 9/27/2016
Title: CONSIDERATION OF AWARDING BID 1617-18 AND APPROVAL OF CONTRACT K-1617-56 BY AND BETWEEN THE NORMAN MUNICIPAL AUTHORITY AND W.L. MCNATT & COMPANY IN THE AMOUNT OF $10,167,000 FOR THE NORMAN FORWARD WESTWOOD FAMILY AQUATIC CENTER PROJECT.
Attachments: 1. Text File Westwood, 2. Bid Record, 3. Waters Edge Recommendation, 4. Westwood Pool Contract with Att A, 5. Engineer Estimate, 6. Contractor's Qualification Statement
Title
CONSIDERATION OF AWARDING BID 1617-18 AND APPROVAL OF CONTRACT K-1617-56 BY AND BETWEEN THE NORMAN MUNICIPAL AUTHORITY AND W.L. MCNATT & COMPANY IN THE AMOUNT OF $10,167,000 FOR THE NORMAN FORWARD WESTWOOD FAMILY AQUATIC CENTER PROJECT.

Body
BACKGROUND: On 13 October 2015, Norman citizens passed the Norman Forward Initiative funding a variety of projects through a 1/2 cent sales tax increase over 15 years. Included in the Norman Forward Initiative was a project to construct a new Westwood Family Aquatic Center.

The Westwood Family Aquatic Center Project includes the demolition of the existing Westwood Swim Complex constructed in 1967 and the construction of a modern, multi-featured facility at this same location.

The Westwood Family Aquatic Center will include a 50 meter lap pool and diving area with a family slide; lazy river; zero depth entry family pool with toddler play features; and a wet deck with dumping buckets and spray features similar to a splash pad. The project also includes a variety of shade features, and a bath house containing an entry/office area, restrooms, showers, changing areas with lockers and a redesigned and enlarged parking lot to accommodate more guests.

DISCUSSION: Bid 1617-18 was advertised in The Norman Transcript, as well as in Construction Market Data, Bid News, Reed Construction Data, Southwest Construction News and e-Plan on 26 August 2016. The pre-bid conference occurred on 6 September 2016, including Parks and Recreation staff, the project design team, seven general contractors and several sub-contractors.

The bid was opened on 15 September 2016. Three complete bids were received, the lowest being from W.L. McNatt & Company, for a total of $10,167,000 including three alternates. The base bid from W.L McNatt & Company is $10,014,000; Alternate No. 1 for an additional open flume slide is $51,000; Alternate No. 3 for the lap pool water heating system is $60,000; and, Alternate No. 4 for additional parking ...