File #: K-1617-114 AMD#4    Version: 1 Name: Amendment No. 4 Griffin Park Sports Complex Project
Type: Contract Status: Passed
File created: 4/29/2020 In control: City Council
On agenda: 6/9/2020 Final action: 6/9/2020
Title: AMENDMENT NO. FOUR TO CONTRACT K-1617-114: BY AND BETWEEN THE NORMAN MUNICIPAL AUTHORITY AND PDG, L.L.C., D/B/A PLANNING DESIGN GROUP, INCREASING THE CONTRACT AMOUNT BY $70,000 FOR A REVISED CONTRACT AMOUNT OF $1,697,650 TO PROVIDE ADDITIONAL PROFESSIONAL ARCHITECTURAL DESIGN SERVICES FOR THE GRIFFIN PARK SPORTS COMPLEX.
Attachments: 1. City Council Staff Report, 2. Amendment 4 K-1617-114, 3. 16-003 Bond Election Outcome - Project Decision Matrix
Title
AMENDMENT NO. FOUR TO CONTRACT K-1617-114: BY AND BETWEEN THE NORMAN MUNICIPAL AUTHORITY AND PDG, L.L.C., D/B/A PLANNING DESIGN GROUP, INCREASING THE CONTRACT AMOUNT BY $70,000 FOR A REVISED CONTRACT AMOUNT OF $1,697,650 TO PROVIDE ADDITIONAL PROFESSIONAL ARCHITECTURAL DESIGN SERVICES FOR THE GRIFFIN PARK SPORTS COMPLEX.

Body
BACKGROUND: On March 14, 2017, the Norman Municipal Authority approved Contract K-1617-114 with PDG, LLC, d/b/a Planning Design Group, in the amount of $761,000 for Professional Architectural Design Services for the Griffin Park Sports Complex.

On August 27, 2019, the Norman Municipal Authority approved Amendment No. 1 to Contract K-1617-114 with PDG, LLC, in the amount of $430,280 for additional Professional Architectural Design Services to add the City Park Maintenance Facility and Transit/Fire Maintenance Facility to the existing contract for the Griffin Park Sports Complex.

On November 12, 2019, the Norman Municipal Authority approved Amendment No. 2 to Contract K-1617-114 in the amount of $120,000 for additional Professional Architectural Design Services to add bidding services and construction administration services for Griffin Park to the contract for work at the Griffin Park Sports Complex.

On April 14, 2020, the Norman Municipal Authority approved Amendment No. 3 to Contract K-1617-114 in the amount of $316,370 for additional Professional Architectural Design Services to provide for an increased project scope and to add bidding services and construction administration services for the City Park Maintenance Facility and Transit/Fire Maintenance Facility to the existing contract for the Griffin Park Sports Complex.

DISCUSSION: As construction phases move forward for the Griffin Park Project, it is now appropriate to add additional scope to the PDG contract which was not covered in the original work.

PDG has proposed additional design fees of $70,000 (see Contract Amendment No. 4) to provide additional services for the...

Click here for full text