Skip to main content
File #: K-1920-91    Version: 1 Name: Jenkins Avenue Widening from Imhoff to Lindsey 2019 Bond Project
Type: Contract Status: Passed
File created: 10/29/2019 In control: City Council
On agenda: 11/26/2019 Final action: 11/26/2019
Title: CONTRACT K-1920-91: A CONTRACT BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND FREESE AND NICHOLS IN THE AMOUNT OF $827,005 TO PROVIDE DESIGN SERVICES FOR THE JENKINS AVENUE WIDENING PROJECT FROM IMHOFF ROAD TO LINDSEY STREET AS PART OF THE 2019 BOND PROJECTS.
Attachments: 1. City Council Staff Report, 2. Location Map, 3. K-1920-91, 4. Contract K-1920-91 Final 11-5-19, 5. 2019 Bond Projects List and Map
Title
CONTRACT K-1920-91: A CONTRACT BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND FREESE AND NICHOLS IN THE AMOUNT OF $827,005 TO PROVIDE DESIGN SERVICES FOR THE JENKINS AVENUE WIDENING PROJECT FROM IMHOFF ROAD TO LINDSEY STREET AS PART OF THE 2019 BOND PROJECTS.

Body
BACKGROUND: On April 2, 2019, the citizens of Norman voted in favor of a $72 million transportation bond issue, which includes nineteen (19) projects. With the anticipated $67 million in federal dollars being leveraged for these projects, approximately $139 million is budgeted for the nineteen (19) projects (please see the attached project list and map showing the approved projects).

On August 19, 2019, City staff advertised Request for Proposal RFP 1920-16 to solicit Consulting Engineering Services for the fourteen (14) bond projects still requiring design. This RFP was written to select a group of approximately five (5) consultants to complete the design on the remaining 2019 Transportation Bond Projects that will be completed over the next ten (10) years. Twenty-two (22) proposals were received by the 4:00 pm deadline on September 12, 2019. The selection committee consisting of three (3) City staff (Scott Sturtz- City Engineer, Tim Miles-Capital Projects Engineer and Paul D'Andrea- Capital Projects Engineer) and two (2) citizens (Luis Malave- ODOT Purcell Resident Engineer and Brent Everett- OU Assistant Director of Architectural & Engineering Services) shortlisted nine (9) consultant teams for interviews held on October 2, 2019. The five (5) consultant teams selected after interviews to complete the design on these projects are:

* Cabbiness Engineering, Norman
* Cowan Group, Oklahoma City
* Freese and Nichols, Oklahoma City
* MacArthur Associated Consultants, Oklahoma City
* Olsson Associates, Oklahoma City

These consultants will be assigned the various projects by City staff based on capacity, performance on their current projects and capabilities of their firm to complete a...