Title
AMENDMENT NO.ONE TO CONTRACT K-1819-133: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND CROSSLAND CONSTRUCTION COMPANY, INC., INCREASING THE CONTRACT AMOUNT BY $5,134,292 TO SET A GUARANTEED MAXIMUM PRICE IN THE AMOUNT OF $5,151,867 TO PROVIDE FOR THE CONSTRUCTION OF THE RUBY GRANT PARK DEVELOPMENT PROJECT AND BUDGET APPROPRIATION FROM THE NORMAN FORWARD FUND BALANCE.
Body
BACKGROUND: On 13 October 2015, the citizens of Norman voted to fund the Norman Forward Quality of Life projects with a limited term 1/2% sales tax increase for 15 years. This initiative included a number of high priority projects identified in the 2014 Library Master Plan Update, the 2009 Norman Parks and Recreation Master Plan and additional projects designed to provide recreational opportunities for Norman residents. One such project was the initial construction of Ruby Grant Park.
DISCUSSION: The Ruby Grant Park project will include entry and parking areas, a competitive cross country trail facility, multi-purpose trails and walkways, dog park, disc golf course, playground area, picnic pavilions, and restroom facilities. Howell and VanCuren, Landscape Architects have completed the construction documents that will be used to build the park improvements.
On April 9, 2019, City Council approved Contract K-1819-133 with Crossland Construction company, Inc. to provide construction management at risk (CMAR) services for the Ruby Grant Park project. The initial contract amount of $17,575 was approved for the purpose of providing pre-construction services which, to date, have included plan review, design assistance, bidding services and value engineering. Construction bids were opened for this project on July 30, 2019. Bid results determined the project to be over the available budget. Since the bid opening, Crossland Construction Company has worked very hard with our design consultants, project management consultants, city staff, and the citizen Ad Hoc Group through a valu...
Click here for full text