Title: CONTRACT K-1920-111: A CONTRACT BY AND BETWEEN THE NORMAN UTILITIES AUTHORITY AND SHAZ INVESTMENT GROUP, L.L.C., AUTHORIZING COLLECTION OF A MONTHLY LIFT STATION FEE FROM DEVELOPED LOTS IN THE TURTLE CROSSING DEVELOPMENT FOR THE OPERATION, MAINTENANCE AND REPLACEMENT OF THE SUMMIT VALLEY LIFT STATION.
Attachments: 1. City Council Staff Report, 2. K-1920-111 - Turtle Crossing LS Agreement, 3. Exhibit A - Turtle Crossing LS Agreement Fees, 4. Exhibit B - Turtle Crossing LS Agreement - Map
Title
CONTRACT K-1920-111: A CONTRACT BY AND BETWEEN THE NORMAN UTILITIES AUTHORITY AND SHAZ INVESTMENT GROUP, L.L.C., AUTHORIZING COLLECTION OF A MONTHLY LIFT STATION FEE FROM DEVELOPED LOTS IN THE TURTLE CROSSING DEVELOPMENT FOR THE OPERATION, MAINTENANCE AND REPLACEMENT OF THE SUMMIT VALLEY LIFT STATION.

Body
BACKGROUND: In 2003, the general policy was modified to allow installation of new lift stations if long-term operation, maintenance and capital equipment replacement costs (OM&R) were borne by the users of the new lift station (LS). An administrative Lift Station Fee collected through utility billing and applicable to each lot or customer in the new development was implemented through a contractual agreement. To date, the Norman Utilities Authority (NUA) has approved eleven lift station agreements as follows:

1. Summit Lakes Addition (K-0304-51 approved 10/14/03);
2. Summit Valley Addition (K-0304-57 approved 10/14/03);
3. Eagle Cliff South Addition (K-0304-58 approved 10/14/03);
4. Cobblestone West Addition (K-0405-119 approved 02/22/05);
5. Alameda Park Addition (K-0506-30 approved 07/12/05);
6. Red Rock Canyon Addition and Park Hill Addition (K-0506-139 approved 05/09/06);
7. Siena Springs Addition (K-0607-70 approved 10/10/06);
8. Links at Norman PUD (K-0809-115 approved 04/14/09);
9. Stone Lake Addition (K-1415-130 approved 04/28/15);
10. The Barn at Terra Verde (K-1819-59 approved 09/24/18); and
11. Eagle Cliff South Section 7 Addition (K-1920-48 approved 09/24/19).

DISCUSSION: The Planning Commission is expected to consider the preliminary plat for Turtle Crossing on February 13, 2020. Sewer service for the proposed Turtle Crossing development will flow south through the existing Eastridge LS. A lift station agreement must be approved by the developer of Turtle Crossing development requiring them to fund a portion of the ongoing OM&R of the existing LS.

As a result of the Summit Valley Interceptor project which will be completed in early 2020, the existing Eastridge LS will be eliminated and the flow will go to the existing Summit Valley LS. The residents currently served by the Eastridge LS and Summit Valley LS will see their LS fee reduced as the annual OM&R costs will be equally distributed between significantly more homes. The revised service area of the Summit Valley LS is shown in Exhibit B of the agreement.

The developer of Turtle Crossing, Shaz Investment Group, LLC, is willing to implement the LS OM&R fee. If acceptable to Council, these costs would be recovered through proposed Contract K-1920-111. The monthly LS fee for the Summit Valley LS is currently $1.83 per household but we be reduced to $1.14 once the Summit Valley Interceptor project is operational. Additionally, for existing homes currently served by the Eastridge LS, the current monthly LS fee of $2.38 will also be reduced to $1.14 since those existing homes will now be served by the Summit Valley LS. The proposed contract provides the following:

1) The LS OM&R fee (the Lift Station Fee) would be filed of record as a restrictive covenant with the final plat of Turtle Crossing as well as any other new areas that ultimately obtain sewer service from the Summit Valley LS.
2) The LS Fee will be adjusted annually to account for inflation and may otherwise be adjusted if changes to the LS service area necessitate an adjustment.
3) In the event a LS is taken out of service and its wastewater flows by gravity to a wastewater treatment facility site, the LS Fee would be discontinued.
4) The LS Fee will be calculated for each dwelling unit as well as a per capita basis to accommodate other zoning classifications such as commercial, institutional, industrial, etc.
5) The LS Fee will be collected monthly from each dwelling unit or non-residential entity contributing flow to the LS through the City's utility billing system.

The calculations for this fee are shown as Exhibit A to the contract while Exhibit B illustrates the expanded area to be served by the Summit Valley LS.

RECOMMENDATION: Staff recommends approval of Contract K-1920-111 implementing the Summit Valley Lift Station Fee for the Turtle Crossing development to the City of Norman.