File #: K-1213-29 CO #1    Version: 1 Name: Final Acceptance of Contract with CGC, Inc., for 24th NW/Legacy Park Drive Traffic Signal and Intersection Project
Type: Contract Status: Passed
File created: 4/25/2014 In control: City Council
On agenda: 5/13/2014 Final action: 5/13/2014
Title: CHANGE ORDER NO. ONE TO CONTRACT NO. K-1213-29: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND CGC, L.L.C., DECREASING THE CONTRACT AMOUNT BY $1,701.30 FOR A REVISED CONTRACT AMOUNT OF $676,668.02 FOR THE 24TH AVENUE N.W. AND LEGACY PARK DRIVE TRAFFIC SIGNAL AND INTERSECTION IMPROVEMENT PROJECT AND FINAL ACCEPTANCE OF THE PROJECT.
Attachments: 1. Text File Change Order Legacy.pdf, 2. Change Order CGC.pdf, 3. Location Map

Title

CHANGE ORDER NO. ONE TO CONTRACT NO. K-1213-29:  BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND CGC, L.L.C., DECREASING THE CONTRACT AMOUNT BY $1,701.30 FOR A REVISED CONTRACT AMOUNT OF $676,668.02 FOR THE 24TH AVENUE N.W. AND LEGACY PARK DRIVE TRAFFIC SIGNAL AND INTERSECTION IMPROVEMENT PROJECT AND FINAL ACCEPTANCE OF THE PROJECT.

 

Body

BACKGROUND:  The University North Park (UNP) Tax Increment Finance District (TIF) was established in July 2006 with plans to provide public financial assistance to the development of the area along 24th Avenue N.W. between Robinson Street and Tecumseh Road.  Up to $54,725,000 of TIF sales and property tax apportionment revenues are authorized for public improvements, of which $11,550,000 is authorized for Traffic and Roadway Improvements.  Some of the improvements include a frontage road extending north from Robinson Street and improvements to up to five intersections along 24th Avenue NW.

 

The intersection of 24th Avenue N.W. and Legacy Park Drive is included in the City’s Capital Improvement Program as one of several University North Park Tax Increment Financing (TIF) projects.  On May 8, 2012, City Council approved Development Agreement No. 5 for the UNP TIF District. Development Agreement No. 5 programmed funding for the construction of Legacy Park and the 24th Avenue NW and Legacy Park Drive Intersection Improvement Project.

 

On August 11, 2009, City Council approved Contract No. K-0910-48 with SMC Consulting Engineers, P.C. (SMC) for the design of both the intersection of 24th Avenue NW and Legacy Park Drive, and the intersection of 24th Avenue N.W. and Rock Creek Road, in the amount of $39,500.  On August 14, 2012, City Council approved Contract No. K-1213-29 with CGC, LLC for the construction of the intersection of 24th Avenue NW and Legacy Park Drive, in the amount of $678,370.12.     

 

DISCUSSION:  Prior to construction of the improvements authorized under Contract No. K-1213-29, Legacy Park Drive was a temporary, one-way road which allowed drivers to access southbound 24th Avenue NW from the retail stores located between Robinson Street and Legacy Park Drive.  Since the completion of the intersection, restaurants, retail stores, and Crest grocery store have been constructed on the east side of 24th Avenue NW and construction of Legacy Park has begun.  The addition of the Legacy Park Drive intersection is crucial to effectively distribute traffic from the new development on the east side of 24th Avenue NW and to provide access to and from Legacy Park after its completion. 

 

The Legacy Park Drive Intersection Improvement Project began construction on August 22, 2012.  The improvements included signalization of the intersection, sidewalks and ramps, and storm water improvements.  Construction was complete on January 18, 2013, seven days ahead of schedule.  Final payment has been made and the total cost of construction was $676,668.82.

 

RECOMMENDATION No. 1Staff recommends that Change Order No. 1 decreasing Contract No. K-1213-29 by $1,701.30 be approved.

 

RECOMMENDATION No. 2Staff further recommends final acceptance of the 24th Avenue NW & Legacy Park Drive Intersection Improvement Project, Contract No. K-1213-29.