File #: K-1213-195 CO#3    Version: 1 Name: K-1213-195 Final Acceptance and Payment
Type: Contract Status: Passed
File created: 2/10/2014 In control: City Council
On agenda: 2/25/2014 Final action: 2/25/2014
Title: CHANGE ORDER NO. THREE TO CONTRACT NO. K-1213-195: BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND DOWNEY CONTRACTING, L.L.C., INCREASING THE CONTRACT BY $5,511.03 FOR A REVISED CONTRACT PRICE OF $1,447,075.60 FOR THE REHABILITATION OF THE CITY OF NORMAN INVESTIGATIONS CENTER LOCATED AT 1507 WEST LINDSEY STREET AND FINAL ACCEPTANCE OF THE PROJECT.
Attachments: 1. Text File Change Orderand Final Police Investigations.pdf, 2. Change Order Downey.pdf

Title

CHANGE ORDER NO. THREE TO CONTRACT NO. K-1213-195:  BY AND BETWEEN THE CITY OF NORMAN, OKLAHOMA, AND DOWNEY CONTRACTING, L.L.C., INCREASING THE CONTRACT BY $5,511.03 FOR A REVISED CONTRACT PRICE OF $1,447,075.60 FOR THE REHABILITATION OF THE CITY OF NORMAN INVESTIGATIONS CENTER LOCATED AT 1507 WEST LINDSEY STREET AND FINAL ACCEPTANCE OF THE PROJECT.

 

Body

BACKGROUND:  On July 9, 2013, City Council approved Contract No. K-1213-195 with Downey Contracting, L.L.C. in the amount of $1,325,500 to renovate the Joe A. Smalley Army Reserve Center at 1507 West Lindsey Street into the City of Norman Investigations Center, with a time frame of 150 days for completion.  The building was acquired through the Base Realignment and Closure process (BRAC) from the federal government with a deed transfer in September 2012, after a seven and a half year process.

 

Change Order # 1, which increased the contract amount by $80,966.19 and extended the term of the contract by fourteen days to December 21, 2013, was approved by City Council on October 22, 2013.  Change Order # 2, which increased the contract amount by $35,098.38 for accessibility modifications, and extended the term of the contract for four weeks to January 18, 2014, was approved by City Council on December 10, 2013 resulting in a revised total contract amount of $1,441,564.54. 

 

DISCUSSION:  Change Order # 3 in the amount of $5,511.03 incorporates twelve changes, most of which were deemed necessary in final inspections of the building.  This final change order brings the total contract sum to $1,447,075.60.  Funds to cover this change order are available in the Smalley Center Renovation project (account number 050-9540-419.61-01; project EF1001).

 

The Certificate of Occupancy was approved on February 11, 2014.  Payments to date have totaled $1,350,257.03, leaving a balance due of $96,818.57.

 

RECOMMENDATION No. 1:  Staff recommends approval of Change Order #3 increasing Contract K-1213-195 by $5,511.03.

 

RECOMMENDATION NO. 2: Staff further recommends final acceptance of the Smalley Center Renovation project for a total contract cost of $1,447,075.60 and final payment in the amount of $96,818.57 to Downey Contracting, L.L.C.