File #: FP-1718-20    Version: 1 Name: Final Plat for St. Thomas More Church
Type: Final Plat Status: Passed
File created: 4/3/2018 In control: City Council
On agenda: 4/24/2018 Final action: 4/24/2018
Title: CONSIDERATION OF A FINAL PLAT FOR ST. THOMAS MORE CHURCH ADDITION, SECTION 2, WITH DEFERRAL OF STREET PAVING AND SIDEWALK REQUIREMENTS FOR JENKINS AVENUE AND ACCEPTANCE OF PUBLIC DEDICATIONS CONTAINED THEREIN. (1535 SOUTH JENKINS AVENUE).
Attachments: 1. Text File, 2. Location Map, 3. Preliminary Plat, 4. Final Plat, 5. Site Plan, 6. Staff Report, 7. Letter, 8. Engineer's Estimate, 9. Application

Title

CONSIDERATION OF A FINAL PLAT FOR ST. THOMAS MORE CHURCH ADDITION, SECTION 2, WITH DEFERRAL OF STREET PAVING AND SIDEWALK REQUIREMENTS FOR JENKINS AVENUE AND ACCEPTANCE OF PUBLIC DEDICATIONS CONTAINED THEREIN.  (1535 SOUTH JENKINS AVENUE).

 

Body

BACKGROUND:  This item is a final plat for St. Thomas More Church, Section 2 and is located at 1535 South Jenkins Avenue (East side of Jenkins Avenue and South of Stinson Street).

 

City Council, at its meeting of December 14, 1999, adopted Ordinance No. O-9900-23, placing a portion of this property in R-1, Single Family Dwelling District with Special Use for a Church.  In addition City Council, at its meeting of June 10, 2014, adopted Ordinance No. O-1314-49, placing the remainder of this property in the R-1, Single Family District and R-3, Multi-Family District with Special Use for a Church.  City Council approved the preliminary plat for St. Thomas More Church Addition, Section 2 at its meeting of June 10, 2014.  The City Development Committee, at its meeting of April 4, 2018, reviewed and approved the program of improvements, site plan and final plat for St. Thomas More Church, Section 2 and recommended that the site plan and final plat be submitted to City Council for consideration including deferral of street paving and sidewalks in connection with Jenkins Avenue. 

 

This property consists of 1.87 acres and one (1) lot with a proposal of a new sanctuary and parking lot.

 

DISCUSSION:  Construction plans have been reviewed for the required public improvements for this property.  The public sanitary sewer main has been relocated.  Additional improvements consist of sidewalk, fire hydrant and street improvements.

 

Approximately 338-feet of Jenkins Avenue will be required to be constructed to City standards as a half-width arterial street. Section 19-602 B 1.2. (a)(b)(c) and (d) of the City Code establishes a method of deferring public street improvements under the following situations: (a) where incompatible grades exist; (b) where there are inadequate or a lack of connecting facilities; (c) where construction of the improvement would not immediately function for its intended use; or (d) where such improvement would be replaced by a planned future project.  The developer is required to post a certificate of deposit with the City in a special account to be used with a future paving project or at such time as development occurs adjacent to the property. Staff has observed over the years that gap paving or “piecemeal” paving has been a detriment to arterial streets. There have been times over the years paving improvements have been constructed and then replaced because they did not fit in the overall design of the arterial street.  Staff is recommending deferral until future development occurs or until the City initiates improvements to Jenkins Avenue. 

 

RECOMMENDATION:  The final plat is consistent with the approved preliminary plat.  Based on the above information, staff recommends acceptance of the public dedications, approval of the final plat and filing of the final plat subject to completion of public improvements. The City Development Committee will ensure completion of all required public improvements or bonds/cash sureties and receipt of a certificate of deposit in the amount of $51,618.65 for deferral of paving and sidewalks.