File #: E-1718-71    Version: 1 Name: Easement for 24th Avenue East Bond Project from Lindsey Street to Robinson Street
Type: Easement Status: Passed
File created: 6/8/2018 In control: City Council
On agenda: 6/26/2018 Final action: 6/26/2018
Title: EASEMENT E-1718-71: ACCEPTANCE OF A PERMANENT PUBLIC ROADWAY, DRAINAGE AND UTILITY EASEMENT FROM THE PENTECOSTAL CHURCH OF GOD, NORMAN, INC., IN THE AMOUNT OF $3,400 FOR THE 24TH AVENUE EAST BOND PROJECT FROM LINDSEY STREET TO ROBINSON STREET.
Attachments: 1. Master Text File, 2. Location Map.pdf, 3. E-1718-71, 4. Easement Table, 5. ROW Acquisition Table, 6. Requistion

Title

EASEMENT E-1718-71:  ACCEPTANCE OF A PERMANENT PUBLIC ROADWAY, DRAINAGE AND UTILITY EASEMENT FROM THE PENTECOSTAL CHURCH OF GOD, NORMAN, INC., IN THE AMOUNT OF $3,400 FOR THE 24TH AVENUE EAST BOND PROJECT FROM LINDSEY STREET TO ROBINSON STREET.

 

Body

BACKGROUND On November 22, 2011, the Norman City Council approved Programming Resolution R-1112-62 requesting federal funds for the 24th Avenue East Bond Project. This resolution states the City’s commitment to adhere to the terms and conditions of a federally funded project including engineering design, acquisition of all necessary rights-of-way and relocation of utilities and encroachments at 100% the City’s cost.  In return, the Association of Central Oklahoma Governments (ACOG), through the Oklahoma Department of Transportation (ODOT), agrees to provide 80% of the construction cost, estimated at $7,831,000, and administration of the construction with the matching share from the City of Norman. 

 

On August 28, 2012, the citizens of Norman voted in favor of a Bond Issue to finance the local share of eight transportation/stormwater improvement projects. One of the eight 2012 bond projects is the 24th Avenue East Bond Project.  Please see the attached location map showing the project boundaries.  The total estimated project cost including design, utility relocations, right-of-way, construction and construction management is $13,008,000.  The City’s share is estimated to be $5,177,000.

 

Proposed improvements for the 24th Avenue East Bond Project include:

 

1.                     Widen two miles of roadway from two lanes to four lanes

2.                     New traffic signal at 24th Avenue East and Meadowood Boulevard

3.                     Intersection improvements at 24th Avenue East/Meadowood Boulevard and 24th Avenue East /Robinson Street

4.                     Interconnect traffic signals on 24th Avenue East from Lindsey Street to Robinson Street

5.                     Continuous sidewalks and accessibility

6.                     Stormwater improvements

7.                     On-street bike lanes

 

On March 12, 2013, City Council approved engineering services Contract K-1213-169 with Atkins North America, Inc., for the design of the 24th Avenue East Bond Project between Lindsey Street and Robinson Street in the amount of $875,266.50.

 

On January 23, 2018, City Council approved Contract K-1718-63 in the amount of $45,413 with Oklahoma Natural Gas (ONG) for Phase 1 (Lindsey to Alameda) utility relocations within private easements.

 

On January 23, 2018, City Council approved the allocation of $74,200 for acquisition services under On-Call Contract K-1314-103 with Pinnacle Consulting Management Group.

 

On February 27, 2018, City Council approved Amendment No. 1 to Contract K-1213-169 with Atkins North America in the amount of $133,455 for additional engineering design services.

 

On April 10, 2018, City Council approved Resolution R-1718-102 creating a Recoupment District for the 24th Avenue East Bond Project.

 

The anticipated remaining project schedule is as follow:

 

                     Continue Utility Relocations and Easement Acquisitions thru Summer of 2018

                     ODOT Bid opening for Phase 1 (Lindsey to Alameda) in October 2018

                     Phase 1 Construction to begin January 2019

                     ODOT Bid opening for Phase 2 (Alameda to Robinson) in February 2019

                     Phase 2 Construction to begin May 2019

 

DISCUSSIONThe City must acquire right-of-way and/or easements from eighteen (18) parcels along 24th Avenue East between Lindsey Street and Robinson Street for the construction of the 24th Avenue East Bond Project. These easements vary in size and type.  To date, six (6) parcels with eight (8) easements have been secured.  Staff requested donations prior to making any offers of fair market value.  The two (2) temporary driveway easements were donated and the six (6) permanent easements accepted compensation for appraised or negotiated values.  The attached table provides the details of each easement. Also, a Right-of-Way Acquisition Sheet is attached providing the location of each easement necessary for the project.  Funds are available within the 24th Avenue East Bond Project BP0192, Account 050-9552-431.60-01, to pay for these easements.

 

RECOMMENDATION Staff recommends the above described easement be accepted, and that payment be authorized, where appropriate, and the filing be directed thereof.